S. No. Name of  Works  Location Client Approx Area Developed (In Sq.ft.) Year of Start Year of Completion Status of Project
1                Construction of 456 Slum Tenements Gp. V - Ph . 1 at Tilak Nagar  DDA  1,68,700 1982 1983 Completed
2 Construction of 192 MIG Houses Mansarover Park DDA 1,85,400 1984 1985 Completed
3 Construction of 240 MIG Houses at Mansarover Park  Mansarover Park DDA 2,31,750 1984 1985 Completed
4 Construction of 272 Slum Tenements N.G. Road DDA 1,00,630 1984 1985 Completed
5 Construction of 256 MIG Houses Kondli / Gharoli DDA 2,30,400 1985 1989 Completed
6 Construction of 256 MIG Houses Kondli / Gharoli DDA 2,30,400 1985 1989 Completed
7 Construction of 108 Houses under SFS(36) Sai - Dul - Jaib , Opp Saket DDA 1,72,000 1987 1989 Completed
8 Construction of 272 LIG / Houses G - 17 , Paschim Vihar Zone DDA 2,58,400 1988 1989 Completed
9 Construction of 128 LIG / Houses Kondli / Gharoli Comaplex DDA 81,200 1989 1990 Completed
10 Construction of 65 Houses SFS Pocket - A & Pocket - B Gp IV , Vasant Kunj DDA 1,17,000 1990 1992 Completed
11 Construction of 72 MIG, 72 LIG Houses Pocket - F , Trilok Puri DDA 1,45,000 1990 1992 Completed
12 Construction of 240 DU's & 40 LIG / Houses Block - D , Pocket - 3 , Bindapur DDA 1,46,000 1991 1993 Completed
13 Construction of 180 MIG / Houses Pocket - 8 , Kundli / Gharoli , Ph- II DDA 1,62,000 1992 1996 Completed
14 Construction of 101 SFS Houses Gazipur DDA 1,56,550 1993 1996 Completed
15 Construction of 120 DU's , 3 BHK , 8 storyed Plot no. - 17 , Sector - 9 , Dwarka Mount Everest Cooperative C.G.H.S Ltd. 2,45,700 1997 1999 Completed
16 Construction of 75 DU's , 3 BHK , 11 storyed  Plot no - 5D , Sector - 11 , Dwarka Shiam CO-OP Gp, Housing Society Ltd. , Dwarka 1,44,500 2001 2004 Completed
17 Construction of 4BHK Houses , 5 storied - 12 towers   Dehradun GTM Builders and Promoters Pvt. Ltd. 2,75,000 2010 2013 Completed
18 Construction of Godawari C.G.H.S. LTD. Multistoried ,  S + 11  Plot No - 39A , Sector - 2 , Faridabad Officers flats Indian Oil Corporation 47,800 2010 2013 Completed
19 Construction of 309 units of  Emilia and Primrose Independent Floors Sector - 83 , Manesar Vatika Pvt. Ltd. 3,60,000 2013 2016 Completed
20 Construction of Parja Cooperative Housing Society , Multistoried , S + 7  Sector - 40 , Plot - 1 , Ludhiana Parja Cooperative Housing Society 2,80,000 2013 In Progress In Progress